How to track project budgets in a small agency
Most projects that go over budget don’t blow up in one week. They drift, a few hours at a time, and nobody notices until the invoice. A budget you check weekly turns that surprise into an early, calm conversation with the client.
Pick the right kind of budget
The budget should match how you sold the work. Otherwise you’re measuring something the client never agreed to.
| How you sold it | Budget in | What you watch |
|---|---|---|
| Fixed fee | Money | Billable value of tracked time against the fee. Over 100% means you’re working for free. |
| Hourly with a cap | Hours | Hours used against the cap. Past 100% you need the client’s OK to keep going. |
| Retainer | Hours or money per month | Hours used this month. Resets each month, so overruns show early. |
| Hourly, no cap | An estimate, in hours | Hours against the estimate you gave, so the client isn’t surprised. |
Hours or money?
Hours are easy for everyone to understand. Money is more accurate when people with different rates work on the same project: 10 hours from a senior strategist uses more of a fee than 10 hours from a junior designer. If your team’s rates vary a lot, budget fixed-fee work in money.
Set alerts before it’s too late to act
An alert at 100% only tells you the budget is gone. The useful one is earlier:
- At 50%, check progress. Is about half the work done? If only a third is, you already know where this is heading.
- At 80%, talk to the client, or make a plan. This is the last point where you have options: cut scope, agree a change request, or accept the overrun knowingly.
- At 100%, stop and decide. Nobody should drift past the budget without someone choosing to.
What to say at 80%
Clients take “we’re at 80% of the budget and here’s what’s left” far better than an overrun on the invoice. Keep it factual:
- Where you are: hours or money used, and what’s been delivered.
- What’s left: the remaining work and your estimate for it.
- The options: trim scope to fit, approve extra hours, or move part of the work to a second phase.
If the overrun comes from something the client asked for (new pages, extra rounds of revisions), it’s a change request, and it’s fair to bill. If it’s your own estimate that was off, decide whether to absorb it, and learn from it for the next quote.
Review budgets weekly
Ten minutes on Monday morning is enough. For every active project, look at:
- Percent of budget used, compared with how much of the work is done
- Hours logged last week, compared with what you expected
- Any project past 80% without a plan
- Retainers on track to run over before the month ends
Track cost, not just billable hours
A project can stay inside its budget and still lose money. To see profit you need two rates for each person:
- Billable rate: what the client pays per hour.
- Cost rate: what that hour costs you, including salary, taxes and overhead, or a contractor’s rate.
An example. A $30,000 fixed-fee website project:
| Person | Hours | Billable rate | Billable value | Cost rate | Cost |
|---|---|---|---|---|---|
| Strategist | 40 | $180 | $7,200 | $90 | $3,600 |
| Designer | 110 | $140 | $15,400 | $65 | $7,150 |
| Developer | 90 | $150 | $13,500 | $75 | $6,750 |
| Total | 240 | $36,100 | $17,500 |
The tracked time is worth $36,100 at your rates, so the project went 20% over its $30,000 fee in money terms. It still earned $12,500 over cost. Both numbers matter: the first tells you the quote was low, the second tells you whether you can afford it.
Retainers: decide what happens to unused hours
Agree up front whether unused retainer hours roll over to next month, expire, or roll over with a limit (for example, up to 25% of the monthly hours). Rolling everything over forever builds up a debt of hours that tends to be called in at the worst moment.
How Sheaf handles this
In Sheaf, every project can have a budget in hours, in money, or as a monthly allowance that resets each month. You get an email at 80% and at 100%, and the overview shows the budgets closest to running out. Each person has a billable rate and a cost rate (with per-project rates if someone bills differently on one project), and reports show billable amount, cost and profit by client, project, task or person. It’s free during beta, and if you use Harvest, your projects and budgets come across with a one-click import.
Try Sheaf free Switching from Harvest
Questions
Should I tell clients about my internal budget?
What if a project goes over budget?
Should non-billable time count against the budget?